Skip to content

Power ON a Dock at Manufacturing EOL

published HW: EV4

This covers initial checks for testing an EV4 Dock, including indications that a dock is powered on and ready.

Applicable to EV4 Dock for powering on at End of Line (EOL) testing or in Maintenance. If the dock is new to EOL testing, start with this procedure before proceeding with the “Communicating with a Dock at EOL” procedure.

1 action
Check that the power cord is fully seated in the dock and plugged into a power source. If the dock is not powered, plug it in and ensure the power source is active.

Did this guide help you get unblocked?